Roadmap Passar 2.0/3.0

The Passar roadmap, as of 23 September 2024, outlines the timeline for the complete replacement of the e-dec application with Passar and the digitalisation of customs procedures. The goal is a gradual implementation by 2027, including the rollout of Passar 2.0 for imports and Passar 3.0 for monitored procedures. Further information can be found through our communication channels.

The chart illustrates the Passar programme roadmap from 2024 to 2027, covering versions 1.0, 2.0, and 3.0. It shows the transition from e-dec Export and Import to Passar, highlighting milestones such as technical documentation, pilot phases, and live operation.

The Passar roadmap forms a joint planning basis for the FOCBS and the private sector for the replacement of the existing e-dec freight application and the digitalisation of monitored procedures and paper forms.

Passar 1.0: transit and exports

  • The changeover for goods in transit has been completed.
  • The changeover from e-dec Export to Passar for exports has to be completed by 31 December 2025 at the latest.

More information

Passar 2.0: imports

Passar 3.0: monitored procedures

The Passar roadmap reflects the planning status as at 23 September 2024. It will be reviewed periodically and updated based on new findings.

The detailed schedule for testing and pilot operation is prepared within the software development working group and with the Operations Directorate, and is coordinated on an ongoing basis.

As usual, news concerning Passar will be actively communicated via the FOCBS's communication channels. We recommend subscribing to our newsletter so that you can be notified by email at all times: www.bazg.admin.ch/news-abo > Passar